Namaste from Nepal. All the structural work on the house for our beneficiary family is complete! Setting wood forms for second slab (roof), setting sun. Steel reinforcement for second slab (roof). Steel reinforcement for second slab (roof) dropped into channels. All we have left is the finishing work, plastering, and installing the window glass and doors. Nepal continues to be one of the most difficult places I have worked—mostly due to the urban location of the site, the desperation of the Nepali people in the face of an inefficient/corrupt government (of the 650,000 homes destroyed in the earthquake over 18 months ago, few others have been rebuilt, even though the government is “sitting on